Proof of concept — demo authentication only, not production secure. All project data shown is synthetic.
◉
COMPASSCentralized Outage & Mobilization Planning, Assurance and Scheduling System · Asia Pacific
Admin DemoAdministrator
SIEMENS
energy
⌄   FILTERS Review month: Oct 2026
TOTAL PROJECTS
7
21 activity bars
NEED ATTENTION
7
CHECKLIST ITEMS OVERDUE
28
EQUIPMENT TYPE
Gas TurbineGeneratorSteam Turbine
ACTIONS OVERDUE
5
NOT REVIEWED THIS MONTH
5
AVG CHECKLIST COMPLETION
46%
BY COUNTRY
Malaysia 2Australia 1Indonesia 1Republic of Korea 1Singapore 1Thailand 1
BY STATUS
In Preparation 3Planning 3Mobilised 1
REGIONAL OUTAGE TIMELINE‹2026–2027›TodayWindow12 months⌄
🔵 Major Inspection🔴 Combustion Inspection🟡 Hot Gas Path🟢 Minor Inspection🟣 Generator Inspection🔷 Mobilisation🌸 Review
PROJECT / SITE
Oct 2026
Nov 2026
Dec 2026
Jan 2027
Feb 2027
Mar 2027
Apr 2027
May 2027
Jun 2027
Jul 2027
Aug 2027
Sept 2027

● Darling Downs GT-02 Major Inspection

AU · Darling Downs Power Station · ● Gas Turbine

● Overall 14%   Chk 25%   2 open   1 overdue

Preparation & MobilisationMajor InspectionClose-out

● Cilegon GT-05 Hot Gas Path

ID · Cilegon Power Complex · ● Gas Turbine

● Overall 10%   Chk 20%   2 open   2 overdue

Preparation & MobilisationHot Gas PathClose-out

● Incheon ST-01 Steam Turbine Overhaul

KR · Incheon Combined Cycle · ● Steam Turbine

● Overall 78%   Chk 50%   1 open

Preparation & MobilisationMajor InspectionClose-out

Project Portfolio

Darling Downs GT-02 Major Inspection

Australia · Gas Turbine · 14% overall

Cilegon GT-05 Hot Gas Path

Indonesia · Gas Turbine · 10% overall

Incheon ST-01 Steam Turbine Overhaul

Republic of Korea · Steam Turbine · 78% overall

Monthly Review

Review regional outage readiness, overdue checkpoints and monthly assurance status across the AP portfolio.

ProjectCountryReadinessChecklistStatus
Darling Downs GT-02Australia14%25%Needs review
Cilegon GT-05Indonesia10%20%Needs review
Incheon ST-01Republic of Korea78%50%In preparation

Review workspace

Darling Downs GT-02

Review overdue

Cilegon GT-05

Review overdue

Action Register

Track readiness actions, owners and due items raised during outage planning and monthly reviews.

ActionProjectOwnerDueStatus
Confirm checklist ownerDarling DownsPlanning teamOct 2026Open
Validate forecast datesCilegonProject teamOct 2026Open

Quick actions

Confirm checklist owner

Open · Darling Downs

Validate forecast dates

Open · Cilegon

+ New action

Add demonstration action

Administration

Demonstration area for portfolio reference data, application access and planning configuration.

Reference Data

User Access

Application Settings